How Long Should My Remodel Process Take: Schedule: As-Builts Through Schematic Design - Cropped for Featured Image

Ask a Designer, Custom Residential

How Long Should My Remodel Process Take?

When you're considering remodeling your house, one of the most unfamiliar aspects is how long it will take from the moment you hire an architect until the moment it is all done and you’re relaxing in your new home. Don't worry, we are here to help with this illustrated post on the process!

August 25, 2015

All of you here in Seattle have seen the towering cranes and the seemingly endless construction sites around this beautiful city. It is boomtown right now, and consequently, things are busy! That means that scheduling out your project takes careful preparation to properly plan your life and ensure that things happen in a reasonable amount of time. I’ve written before about how long it takes to truly plan a remodel, but I wanted to go into more detail to illustrate what you should expect when thinking about remodeling your home.

I’ve built a generic project schedule for a typical remodel we see here: a second-story addition to a house in Seattle. Assume that the lot is normal (no steep slopes or crazy wetlands… seriously watch for frogs - they can trip you up), that there is no General Contractor selected, and that it will require a full permit review. I've shown a contract signing date of September 1, 2015 so you can understand roughly when things happen after that. This assumes a pretty normal and not overly-aggressive schedule, and should help you understand the different items in play.

How Long Does a Remodel Take? – Overall Schedule
Overall Schedule

The overall schedule moves from phase to phase with some minor overlap, as needed, to keep things moving.

First we'll measure the house, then run through a general analysis (pre-design) of the site, and then dive into Schematic Design. If you want to know more about that process you can check out my recap here.

Once we complete Schematic Design, we’ll use our Schematic Pricing set to get an update on where we are in terms of cost. We’ll define and tweak the scope, and then move ahead selecting a General Contractor, and clarifying the scope of work. Note that sometimes the “value engineering” portion can take much longer than the one week allotted here, as it involves a long process of weighing the pros and cons of what you include in your remodel to meet your budget. Here's some additional thoughts on finding that contractor.

How Long Does a Remodel Take? – The Stages of Architectural Design – Comparison Spreadsheet for Bidding
Bidding

Comparison spreadsheets like this are assembled from the different estimates so we can accurately compare “apples to apples.”

Now, we dive into the permit set. These days, even calling for a permit intake appointment in Seattle can mean that you don’t get an appointment for 2 months. (Remember all those building cranes? Yeah, they’re slowing things down at the city). There’s a lot that happens here, and even after we submit, there will be corrections and some time spent processing that. This length of time is a big variable, and it is best to leave a lot of slop here to plan for the unexpected.

How Long Does a Remodel Take? – Project Schedule: Design Development & Permitting
dd - 1

The first part of the Design Development and Permitting phase involves lots of lining things up to ensure things move smoothly.

How Long Does a Remodel Take? – Project Schedule: Permit Submittal
dd - 2

Once we submit for permit, there's still a very normal back and forth with the city for permit corrections.

After we submit for permit, we will actually dive into pulling together the construction documents to wrap up supplemental details needed by the contractor. It is at this phase that we’ll typically finalize a lot of the interior finishes and details. Once we get the final permit corrections, we’ll wrap them into this set and then issue the final set of construction documents.

How Long Does a Remodel Take? – Project Schedule: CD and CO
CD and CO

The later phases of the project take more time and are far more detailed.

When construction begins, we are almost nine months from the signing of the contract. Add another six months for construction (that is a big variable depending on your scope of work, as it could easily be nine months or more), and you’re looking at least 15 months for your total project duration.

The other factor to consider, of course, is when your design team can start. We are divided into teams here, with each team having different availability for their project load. Some teams are almost six months out at this point, while others still have some availability in a few months. It changes weekly, of course, so being able to lock things in with our clients earlier on helps us plan ahead and feel confident with the schedule.

From my conversations with clients, there’s unfortunately a clear misunderstanding about how long this process takes. (Things don't happen as quickly as you see on TV!) I hear easily 75% of the time when talking to someone about their project, that they’d like to be done in no more than 12 months (often even four or six months). As you can see from the diagrams above, that timeline is very challenging, or impossible for a project with full permit review. We’re always happy to walk you through options to expedite the schedule, but if you go into it knowing how long things should take if done properly, you’ll be able to manage your expectations and come out with a better project. And, of course, when you work with us, we’ll give you a tailored schedule to help you move forward.

Would you like to read more from the team?

If you enjoy reading our blog as much as we enjoy writing it, that just makes our day! You might also enjoy a few of the related posts below. And, if there is a topic that you wish we would cover, let us know!

The Middle Housing Bill FAQ

Washington State’s HB1110 — also called the Middle Housing Bill — is setting the stage for big changes to code and zoning in Seattle. But what is middle housing? And what is the “missing middle” HB1110 seeks to fill? You have questions and we have answers based on our best, current understanding of this landmark legislation.

Do I Need a Feasibility Study?

A lot of questions come up when you embark on a design project. A lot of questions come up before embarking on a design project! A feasibility study, especially for complex or potentially complicated sites or projects, might be just what you need to kick off a successful project.

What To Consider When Future-Proofing Your Home

How long do you plan to stay in your current home? If you’re considering staying in it through your golden years, you’ll want to start thinking about future-proofing. Confused? Don’t worry! Here, we’ll walk you through the four basic principles to follow when you’re planning to age in place.

Considering a project, or curious about something?

Say hello, and send us your questions via the form below. We’re always pleased to make new connections, and eager to get to know you, your project, and your goals.

Get in touch.